Villanova University

Project Overview:

Tore off existing canopy roof down to light weight concrete desk.

Installed 2 layers of 2.6″ insulation set in adhesive, adhered in coverboard, adhered TPO.

New drains, counter flashings, and edge metal were installed.

  • Type of Project:

    Full Tear Off Replacement
  • Location:

    Villanova, PA
  • Building Type:

    Dorm
  • Completion Date:

    December 2024

Project Goals & Requirements:

  • Client’s Requirements:

    Completed during Christmas break
  • Project Objectives:

  • Unique Challenges:

    Cold weather

Roofing System & Materials Used:

  • Type of Roofing System Installed:

    Adhered TPO
  • Materials and Brands Used:

    Johns Manville
  • Reason for Choosing this System:

    Preferred brand of Villanova

Installation Process & Highlights:

  • Work was completed in 1 week with temperatures in the 30s.